1.3
     1.3.1 c 22 January 2021 22 January 2021
TA Requirments
     1.3.2 c 22 January 2021 22 January 2021
TA Requirments
     1.3.3 c 22 January 2021 22 January 2021
TA Requirments
     1.3.4 c 22 January 2021 22 January 2021
TA Requirments
Implementation Date
Article Type Indicative Definitive Additional Information
7.8
     7.8.1 c 22 February 2021 22 February 2021
TA Requirments
           7.8.1 (a) c 22 February 2021 22 February 2021
TA Requirments
           7.8.1 (b) c 22 February 2021 22 February 2021
TA Requirments
           7.8.1 (c) c 22 February 2021 22 February 2021
TA Requirments
           7.8.1 (d) c 22 February 2021 22 February 2021
TA Requirments
           7.8.1 (e) c 22 February 2021 22 February 2021
TA Requirments
           7.8.1 (f) c 22 February 2021 22 February 2021
TA Requirments
           7.8.1 (g) c 22 February 2021 22 February 2021
TA Requirments
           7.8.1 (h) c 22 February 2021 22 February 2021
TA Requirments
     7.8.2 c 22 February 2021 22 February 2021
TA Requirments
           7.8.2 (a) c 22 February 2021 22 February 2021
TA Requirments
           7.8.2 (b) c 22 February 2021 22 February 2021
TA Requirments
           7.8.2 (c) c 22 February 2021 22 February 2021
TA Requirments
           7.8.2 (d) c 22 February 2021 22 February 2021
TA Requirments
     7.8.3 c 22 February 2021 22 February 2021
TA Requirments
Implementation Date
Article Type Indicative Definitive Additional Information
10.5
     10.5.1 c 31 December 2021 31 December 2021
TA Requirments
     10.5.2 c 31 December 2021 31 December 2021
TA Requirments

Legend

A Fully notified in A
Ap Partially notified in A
N Not yet notified
B Fully notified in B
Bp Partially notified in B
CB Shift from C to B
E Extension of time requested
C Fully notified in C
Cp Partially notified in C
BC Shift from B to C
Arrangements & Progress

Notification Status