Implementation Date |
||||||
---|---|---|---|---|---|---|
Article | Type | Indicative | Definitive | Deadline for extension request, if required | Additional Information | |
12.1 | b | 30 June 2022 | 30 June 2024 |
|
||
12.1.1 | b | 30 June 2022 | 30 June 2024 |
|
||
12.1.2 | b | 30 June 2022 | 30 June 2024 |
|
||
12.2 | b | 30 June 2021 | 30 June 2024 |
|
||
12.2.1 | b | 30 June 2021 | 30 June 2024 |
|
||
12.2.2 | b | 30 June 2021 | 30 June 2024 |
|
||
12.3 | a | 22 February 2018 |
|
|||
12.4 | b | 30 June 2021 | 30 June 2024 |
|
||
12.4.1 | b | 30 June 2021 | 30 June 2024 |
|
||
12.4.1 (a) | b | 30 June 2021 | 30 June 2024 |
|
||
12.4.1 (b) | b | 30 June 2021 | 30 June 2024 |
|
||
12.4.1 (c) | b | 30 June 2021 | 30 June 2024 |
|
||
12.4.1 (d) | b | 30 June 2021 | 30 June 2024 |
|
||
12.4.1 (e) | b | 30 June 2021 | 30 June 2024 |
|
||
12.4.1 (f) | b | 30 June 2021 | 30 June 2024 |
|
||
12.4.2 | b | 30 June 2021 | 30 June 2024 |
|
||
12.5 | b | 30 June 2021 | 30 June 2023 |
|
||
12.5.1 | b | 30 June 2021 | 30 June 2023 |
|
||
12.5.1 (a) | b | 30 June 2021 | 30 June 2023 |
|
||
12.5.1 (b) | b | 30 June 2021 | 30 June 2023 |
|
||
12.5.1 (c) | b | 30 June 2021 | 30 June 2023 |
|
||
12.5.1 (d) | b | 30 June 2021 | 30 June 2023 |
|
||
12.5.1 (e) | b | 30 June 2021 | 30 June 2023 |
|
||
12.5.1 (f) | b | 30 June 2021 | 30 June 2023 |
|
||
12.5.2 | b | 30 June 2021 | 30 June 2023 |
|
||
12.5.3 | b | 30 June 2021 | 30 June 2023 |
|
||
12.6 | b | 30 June 2021 | 30 June 2024 |
|
||
12.6.1 | b | 30 June 2021 | 30 June 2024 |
|
||
12.6.1 (a) | b | 30 June 2021 | 30 June 2024 |
|
||
12.6.1 (b) | b | 30 June 2021 | 30 June 2024 |
|
||
12.6.1 (c) | b | 30 June 2021 | 30 June 2024 |
|
||
12.6.1 (d) | b | 30 June 2021 | 30 June 2024 |
|
||
12.6.1 (e) | b | 30 June 2021 | 30 June 2024 |
|
||
12.6.2 | b | 30 June 2021 | 30 June 2024 |
|
||
12.7 | b | 30 June 2021 | 30 June 2023 |
|
||
12.7.1 | b | 30 June 2021 | 30 June 2023 |
|
||
12.7.1 (a) | b | 30 June 2021 | 30 June 2023 |
|
||
12.7.1 (b) | b | 30 June 2021 | 30 June 2023 |
|
||
12.7.1 (c) | b | 30 June 2021 | 30 June 2023 |
|
||
12.7.1 (d) | b | 30 June 2021 | 30 June 2023 |
|
||
12.7.1 (e) | b | 30 June 2021 | 30 June 2023 |
|
||
12.7.2 | b | 30 June 2021 | 30 June 2023 |
|
||
12.8 | b | 30 June 2021 | 30 June 2024 |
|
||
12.9 |
b
C B
|
30 June 2021 | 30 June 2024 |
|
||
12.9.1 |
b
C B
|
30 June 2021 | 30 June 2024 |
|
||
12.9.2 |
b
C B
|
30 June 2021 | 30 June 2024 |
|
||
12.10 | b | 30 June 2020 | 30 June 2024 |
|
||
12.10 (a) | b | 30 June 2020 | 30 June 2024 |
|
||
12.10 (b) | b | 30 June 2020 | 30 June 2024 |
|
||
12.10 (c) | b | 30 June 2020 | 30 June 2024 |
|
||
12.10 (d) | b | 30 June 2020 | 30 June 2024 |
|
||
12.10 (e) | b | 30 June 2020 | 30 June 2024 |
|
||
12.10 (f) | b | 30 June 2020 | 30 June 2024 |
|
||
12.10 (g) | b | 30 June 2020 | 30 June 2024 |
|
||
12.10 (h) | b | 30 June 2020 | 30 June 2024 |
|
||
12.11 | b | 30 June 2021 | 30 June 2023 |
|
||
12.11.1 | b | 30 June 2021 | 30 June 2023 |
|
||
12.11.1 (a) | b | 30 June 2021 | 30 June 2023 |
|
||
12.11.1 (b) | b | 30 June 2021 | 30 June 2023 |
|
||
12.11.1 (c) | b | 30 June 2021 | 30 June 2023 |
|
||
12.11.2 | b | 30 June 2021 | 30 June 2023 |
|
||
12.12 | b | 30 June 2021 | 30 June 2024 |
|
||
12.12.1 | b | 30 June 2021 | 30 June 2024 |
|
||
12.12.2 | b | 30 June 2021 | 30 June 2024 |
|
Legend
A | Notified in Cat. A |
Ap | Partially notified in A |
N | Not yet notified |
B | Notified in Cat. B |
Bp | Partially notified in B |
CB | Shift from C to B |
E | Extension of time requested |
C | Notified in Cat. C |
Cp | Partially notified in C |
BC | Shift from B to C |
Arrangements & Progress |