Mali
Articles |
7.4.1
–
7.4.2
–
7.4.3
–
7.4.4
View measure text |
---|---|
Indicative date of implementation | 31 December 2023 |
Definitive date of implementation | 31 December 2026 |
Deadline for extension request, if required | 2 October 2026 |
Assistance required for implementation |
- Training for customs and other officials on the issuing, receipt, processing, publication and follow-up of classification decisions - Legal expertise for drafting legal texts and amendments to existing ordinances, laws and regulations - Expert support for the design and establishment of a risk management system - ICT infrastructure for an automated risk management system - Staff capacity-building with a view to implementing the risk management system |
Donor / Agency |
World Bank, Trade Facilitation Programme in West Africa |
Progress reported |
19 February 2021 — G/TFA/N/MLI/2Assessment and development of an integrated risk management strategy. |