Saint Kitts and Nevis
Articles |
10.4.1
–
10.4.2
–
10.4.3
–
10.4.4
View measure text |
---|---|
Indicative date of implementation | 31 December 2021 |
Definitive date of implementation | 31 December 2024 |
Extension of time |
Request received
14 July 2022
Original definitive date
31 December 2023
New date requested
31 December 2024
Date approved
31 December 2024
Reason
The recovery initiatives from the debilitating economic impact of COVID-19 warranted a major shift of priorities for the agencies needed to meet the original definitive date. Henceforth, the legislative amendments, procedures, human resource - capacity building, the required ICT and technical infrastructure etc. needed to complete Article 10.4 – Single Window was not possible.
The Second wave of COVID-19 worsened the situation in St. Kitts and Nevis.
Committee approval:
Approved
Link to notification
|
Assistance required for implementation |
• Legal/Policy - technical assistance to review relevant laws in order to develop comprehensive nation single window; • Technical assistance needed leading to setting a clear time scale of Single Window role out and implementation; • Procedures - development of efficient procedures and checklist in order to implement national single window effectively; • Institutions - technical assistance to build capacity in relevant border agencies in order to implement national single window; • Human Resources/Training capacity building needed for relevant border agency Officials and business community to be sensitised, equipped and trained in order to implement national single window; • ICT –assistance to ensure reasonable to high level access to IT equipment's especially for other border agencies; • Infrastructure/Equipment – assistance required in setting up and installing appropriate IT equipment's and systems in some agencies and at ports of entry. |
Donor / Agency | Not yet notified |
Progress reported | Not yet notified |