Sri Lanka
Articles |
5.1 (a), (b), (c), (d)
View measure text |
---|---|
Indicative date of implementation | 31 December 2020 |
Definitive date of implementation | 30 June 2023 |
Extension of time |
Request received
20 August 2021
Original definitive date
31 December 2021
New date requested
30 June 2023
Date approved
30 June 2023
Reason
• Covid-19 Pandemic situation
• Difficulties in finding a donor agency
Committee approval:
Approved
Link to notification
|
Assistance required for implementation |
• Legal expert support on drafting legal amendments to existing ordinances/ acts/regulations. • Expert support on the design and establishment of a notification system for enhanced controls or inspections. • Staff capacity building on implementing a notification system for enhanced controls or inspections. • ICT Infrastructure for establishing an automated notification system. |
Donor / Agency | Not yet notified |
Progress reported | Not yet notified |