Barbados
Ratified on the 31 January 2018
Status of implementation commitments
Rate of current and future implementation commitments according to notification data
The current rate of implementation commitments stands at 44.5% with a time-frame spanning from February 2017 to December 2028
Search implementation commitments by date:
Full implementation plans
Full notification breakdown
6 measures due for implementation
2022-2023
13 measures notified in Cat. C
Technical Assistance dedicated page
2 measures shifted between categories
Status of Notification
Implementation Notifications (Categories A, B, C) | Due date | Status | |
---|---|---|---|
Notified all category ABC designations | by 22 February 2017 | Yes | |
Notified indicative dates in Category B | by 22 February 2017 | Yes | |
Notified definitive dates in Category B | by 22 February 2018 | Yes | |
Notified indicative dates in Category C | by 22 February 2017 | Yes | |
Notified definitive dates in Category C | by 22 August 2019 | Yes | |
Notified Technical Assistance requirements | by 22 February 2017 | Yes | |
Notified arrangements on the provision of technical assistance support | by 22 February 2018 | No | |
Notified progress in the provision of technical assistance support | by 22 August 2019 | No | |
Transparency notifications | |||
Notified Art. 1.4 | Category C | Definitive implementation date 31 December 2028 | No |
Notified Art. 10.4.3 | Category C | Definitive implementation date 31 December 2025 | No |
Notified Art. 10.6.2 | Category B | Definitive implementation date 31 December 2020 | Yes |
Notified Art. 12.2.2 | Category B | Definitive implementation date 31 December 2022 | Yes |
Information on Assistance and Capacity Building | |||
Notified Art. 22.3 | No |
Legend:
Yes
Notification presented
No
Notification due
No
Notification not yet due