Grenada
Articles |
10.4.1
–
10.4.2
–
10.4.3
–
10.4.4
View measure text |
---|---|
Indicative date of implementation | 31 December 2021 |
Definitive date of implementation | 30 June 2030 |
Deadline for extension request, if required | 2 March 2030 |
Extension of time |
Request received
17 October 2022
Original definitive date
31 December 2028
New date requested
31 December 2031
Date approved
30 June 2030
Reason
Grenada has been working on the single window with a donor agency and was successful in getting a few border agencies on-board with a partial electronic single window. However, to fully implement this measure, additional technical assistance is needed hence the reason for the extension.
Committee approval:
Approved new date
Link to notification
|
Assistance required for implementation |
Assistance needed: Legal/Policy Technical Assistance to review relevant legislations from different border agencies to develop one single window to be used by all border agencies. Technical Assistance for setting clear time scale for roll out and implementation of Single Window. Procedures Assistance to develop efficient and effective procedures in order to implement national single window. Human Resource/Training Training and capacity building for relevant border agencies. Sensitization of business community in order to implement single window. |
Donor / Agency | Not yet notified |
Progress reported | Not yet notified |