10.6.1
–
10.6.2
–
10.6.3
View measure text |
---|---|
Indicative date of implementation | 31 December 2021 |
Definitive date of implementation | 30 June 2026 |
Extension of time |
Request received
19 September 2024
Original definitive date
30 December 2024
New date requested
30 June 2026
Date approved
30 June 2026
Reason
Lack of donor assistance and support for capacity building required for implementation of this category C measure.
Committee approval:
Approved
Link to notification
Request received
1 March 2023
Original definitive date
30 June 2023
New date requested
30 December 2024
Date approved
30 December 2024
Reason
Lack of donor assistance and support for capacity building required for implementation of this category C measure
Committee approval:
Approved
Link to notification
Request received
13 September 2021
Original definitive date
31 December 2021
New date requested
30 June 2023
Date approved
30 June 2023
Reason
No technical assistance and Capacity Building received for the Implementation of projects.
Shift in the Implementation timeframe of work plans due to COVID-19 pandemic.
Committee approval:
Approved
Link to notification
|
Assistance required for implementation |
• Review licensing requirements to ensure that they are objective and transparent; • Training on publication requirements; • Technical assistance in design and development of a system integrated profiling mechanism for brokers; • Assistance for awareness creation and training for the roll-out of new system; • Technical assistance (funding) to train brokers on customs procedures. Develop policy/procedures/monitoring to ensure that procedures are applied uniformly throughout the country; • Technical assistance and support to streamline and optimize border processes and procedures with all institutions in order to ensure improved controls, eliminate unnecessary formalities and harmonize requirements for safeguarding international good practices. |
Donor / Agency | Not yet notified |
Progress reported | Not yet notified |