Pakistan
Articles |
1.2.1 (a), (b), (c)
Texte de la mesure |
---|---|
Date indicative de mise en oeuvre | 30 juin 2019 |
Date définitive de mise en oeuvre | 31 mars 2022 |
Demande de report des dates |
Request received
30 juin 2020
Original definitive date
30 septembre 2020
New date requested
31 mars 2022
Date approved
31 mars 2022
Reason
All the required information is now available on the Federal Board of Revenue website, however, the online portal to make available some Customs and trade related information necessary to meet the implementation of this provision is still being developed and the planning for the portal development has been affected by the health crisis. Similarly, the required update for the ICT funded by the World Bank is still ongoing.
Committee approval:
Approved
Link to notification
|
Assistance requise pour la mise en oeuvre | Élaboration de projet et compétences informatiques pour les RH, assistance liée au matériel informatique et aux logiciels pour alignement sur les meilleures pratiques internationales. |
Donateur / Agence | Pas encore de notification |
Progrès rapporté | Pas encore de notification |
Articles |
1.2.3
Texte de la mesure |
Date indicative de mise en oeuvre | 30 juin 2019 |
Date définitive de mise en oeuvre | 31 mars 2022 |
Demande de report des dates |
Request received
30 juin 2020
Original definitive date
30 septembre 2020
New date requested
31 mars 2022
Date approved
31 mars 2022
Reason
All the required information is now available on the Federal Board of Revenue website, however, the online portal to make available some Customs and trade related information necessary to meet the implementation of this provision is still being developed and the planning for the portal development has been affected by the health crisis. Similarly, the required update for the ICT funded by the World Bank is still ongoing.
Committee approval:
Approved
Link to notification
|
Assistance requise pour la mise en oeuvre | Infrastructures/travaux publics, développement de logiciels, matériel informatique de réseau, renforcement des capacités des RH. |
Donateur / Agence | Pas encore de notification |
Progrès rapporté | Pas encore de notification |