Pakistan

8 - Coopération entre les organismes présents aux frontières

Articles 8.18.2 (a), (b), (c), (d), (e)
Texte de la mesure
Date indicative de mise en oeuvre 30 juin 2020
Date définitive de mise en oeuvre 30 juin 2026
Date limite pour un report des dates, si nécessaire 2 mars 2026
Report des dates de mise en œuvre
Demande reçue
20 février 2026
Date définitive originale
30 juin 2026
Nouvelle date demandée
31 décembre 2026
Date convenue
Raison
• Pakistan has partially implemented Article 8 by allocating dedicated physical space for Afghan Customs at the Torkham and Chaman border crossing points (BCPs) for intended joint Customs controls. • The cross-border hostilities have currently stopped. The relevant authorities have been instructed to conduct a detailed assessment of the damage to buildings, infrastructure, and equipment. Work on operationalization is ongoing, including site acceptance testing (SAT) at Torkham, and repair/rectification and integration activities at Chaman, subject to the prevailing security situation. • The deployment of Afghan Customs personnel to utilize the dedicated space in Torkham and Chaman Customs Houses is contingent on conclusion of the requisite bilateral arrangement between the two counterpart Customs Administrations. • In view of the foregoing, Pakistan requests an additional six months, until 31 December 2026, to finalize restoration work, subject to the prevailing security conditions, in order to fully implement Article 8.
Approbation du comité
En attente
Lien vers la notification

Demande reçue
17 avril 2025
Date définitive originale
30 juin 2025
Nouvelle date demandée
30 juin 2026
Date convenue
30 juin 2026
Raison
• Pakistan was on course to implement the remaining elements of Article 8, i.e. establishment of joint border controls between Pakistan and Afghanistan by 30 June 2025. However, security situation escalated in March 2025, resulting in significant damage to the critical infrastructure and evacuation of staff Members of Project Management Unit and the National Logistic Cell (NLC) [the terminal operator at Torkham border crossing point (BCP)]. The NLC also issued a 'notice of force majeure' [indicating difficulty to continue cross border trade and transit activities] due to security unrest at the across Pak Afghan border at Torkham • NLC has been instructed to conduct a detailed damage assessment of buildings, infrastructure, and equipment along-with estimation of cost and time required for repair and replacement. However, due to continued security volatility across the Pakistan-Afghanistan border, NLC has not been able to complete the assessment process so far.
Approbation du comité
Approuvé
Lien vers la notification

Demande reçue
5 août 2024
Date définitive originale
31 décembre 2024
Nouvelle date demandée
30 juin 2025
Date convenue
30 juin 2025
Raison
The delay in implementing Article 8 of the TFA was caused by the following unforeseeable factors: • Project Management Unit (PMU), Integrated Transit Trade Management System (ITTMS) has awarded contract for reengineering, digitization, and integration of cross-border trade processes that is scheduled for completion by 31 January 2025. Once the physical and digital infrastructure is in place, configuration and final user testing may require up to five months. • The establishment of joint control between Pakistan and Afghanistan requires a bilateral agreement, which is currently under negotiation. Even though the infrastructure would be in place by early 2025, the commissioning will depend on the outcome of these ongoing negotiations. • An extension in the implementation of the provision is required until 30 June 2025 for achieving the final operationalization of both Torkham and Chaman Border Land Ports.
Approbation du comité
Approuvé
Lien vers la notification

Demande reçue
24 juin 2020
Date définitive originale
30 juin 2023
Nouvelle date demandée
31 décembre 2024
Date convenue
31 décembre 2024
Raison
Project Management Unit (PMU), Integrated Transit Trade Management System ITTMS, FBR is implementing this initiative with assistance from Asian Development Bank (ADB). However, the current health crisis context will require an extra delay for the execution of all planned implementation processes.
Approbation du comité
Approuvé
Lien vers la notification
Assistance requise pour la mise en oeuvre Assistance informatique, établissement d'un système d'échange électronique de données (EDI) avec les autorités douanières des pays frontaliers, établissement d'un guichet unique national.

Étiquettes: Technologies de l’information et de la communication (TIC), Procédures institutionnelles

Donateur / Agence Pas encore de notification
Progrès rapporté Pas encore de notification